Engineering services – feasibility study module 1 – district heating network BEW subsidy
Original: Engineering services – 62-2026-061-EA - Machbarkeitsstudie Modul 1 - BEW-Förderung für ein Wärmenetzsystem und vertiefende Planungsleistungen im zweiten Entwicklungsabschnitt in der ehem. Prinz-Leopold-Kaserne
Stadt Regensburg
- Value
- Not stated · check listing
- Closes
- 8 Jun 2026Closing date passed
- Where
- Germany
- Contract
- Consulting · Government
In context
This is a contract notice published by a government body covering consulting. Bids are invited through an open procedure. Delivery covers Germany and the European Union (Europe). It is classified under Heating and Cooling, Renewable Energy and Energy Efficiency and 1 other against the sustainability taxonomy rather than matched on keywords.
Summary
City of Regensburg seeks engineering services to conduct a feasibility study and preliminary design (HOAI phases 1–4) for a district heating network across a former military barracks, integrating renewable energy and PV planning. The ideal bidder is an experienced engineering consultant with expertise in district heating systems, energy efficiency, BEW-programme compliance, and integrated energy planning for urban quarters.
This tender has closed
Similar tenders are open now. Pro keeps the official link on every listing, closed ones included.
About this tender
The City of Regensburg (Stadt Regensburg) is procuring engineering services for a feasibility study (Modul 1) under the German Federal Funding for Efficient Heat Networks (Bundesförderung für effiziente Wärmenetze - BEW), along with in-depth planning services for a heat network system in the second development phase of the former Prinz-Leopold-Kaserne (Prince Leopold Barracks) area in Regensburg. The aim is to realize the second development phase and couple it with the first phase to provide integrated and sustainable heat supply for the entire quarter. The scope of services includes preparation of the feasibility study including planning according to service phases (LPH) 1-4 of the HOAI, technical concept development, and coordination services upon a positive funding decision. Additionally, planning services outside the funding framework must be provided for the energy quarter development, particularly electrical and PV planning. The planning will examine technical and economic feasibility with the goal of implementation under Modul 2 of the BEW. The contract has a minimum duration of 9 months for Modul 1, which may extend to 9-12 months depending on the timing of the funding decision. The contract is conditional on BAFA approving the funding application — if BAFA rejects funding, the City reserves the right not to award the contract and to cancel the procurement. Optional services include: optional extension of project duration by up to 12 months if justified; preparation and submission of the Modul 2 funding application (optional extension by up to a further 12 months); and coordination services for Modul 2 (optional extension by up to a further 4 years plus optional further 2 years).
Bidder eligibility
Bidders must not be subject to exclusion grounds under §§ 123-126 GWB and must declare any relations to Russia (Eigenerklärung Bezug Russland - FB 127/L127/III.127). Required qualifications include: - Turnover: company turnover in the last three completed financial years for comparable services. - Professional liability insurance: coverage of EUR 3,000,000 for personal injury and EUR 3,000,000 for other damages, with maximum benefit per insurance year at least twice the coverage sum. - Registration in a relevant professional register and membership in the trade association (Berufsgenossenschaft). - Team requirements: Project leader with relevant university degree and min. 10 years experience in the energy sector with competence in heat network planning, MSR, or electrical planning; Deputy with min. 5 years experience; staff members with min. 3-5 years experience. - Eight references (R1-R8) required, completed between 01/01/2019 and 01/04/2026: R1 & R2: Two reference projects for Modul 1 BEW implementation (study area min. 1 MW heating capacity) with completed feasibility studies under BEW or predecessor program 'Wärmenetze 4.0'. R3 & R4: Two reference projects with successfully submitted Modul 2 BEW funding applications that received positive funding decisions. R5: Geothermal planning with min. 30 probes through approval planning (LPH 1-4). R6: Wastewater-based heat supply with min. 100 kW thermal capacity through approval planning. R7: Energy center planning with min. 500 kW thermal capacity, min. 75% renewable energy share (excluding biomass/biogas/biomethane/biofuels), with heat pumps plus another independent heat generator. R8: Electrical installation planning with min. 4 MW connection capacity, min. 10 kV MV voltage, min. 100 m line length, and min. on
How bids are scored
Award is based on the most economically advantageous tender. Price is not the sole award criterion. Disclosed weightings: Price 60%, Quality (remaining weighting per tender documents). The quality score is determined by evaluation of a submitted procedural concept (Vorgehenskonzept) of max. 25 A4 pages (Arial 11, line spacing 1-1.5) covering: project understanding (BEW Modul 1 objectives, local conditions, opportunities and challenges); methodological approach (data collection, network simulation, economic calculations, scenario development, evaluation of heat sources including renewables/waste heat/CHP, network concept selection, integration of BEW requirements including minimum renewable share and innovation level); work steps, schedule, and resource planning with phases, milestones, and resource distribution; and work organization and collaboration including digital tools/platforms. Full criteria are detailed in tender document 62-2026-061-EA_A04_Leistungsbeschreibung.
Key requirements
- Feasibility study (Modul 1) per BEW federal funding programme for efficient district heating networks
- Design planning per HOAI phases 1–4, including technical concept and economic viability assessment
- Integration of phase 2 development with existing phase 1; coordinated sustainable heat supply for entire quarter
- Electrical and PV planning outside the BEW funding scope
- Coordination with City of Regensburg throughout execution
Procurement contact
The notice names a procurement contact for clarification questions.
CPV codes
CPV codes
How this compares
About this sector
About this sector
Heating and cooling funding supports heat pumps, district heating, thermal networks, efficient cooling and the removal of fossil boilers. It arrives through national support schemes, local authority programmes and procurement for heat networks. Applicants typically need heat demand assessments, a connection plan and an operator for the system.
This opportunity has closed. Find the next one
Create a free account and we save a search for this sector and country, so new tenders like this one arrive in your weekly email.
Alert me to similar opportunities →Quick facts
Documents to prepare
We found no document list in this notice. Usually asked for in tenders and RFPs; typical only, not this buyer’s list. Check the official notice.
- Technical proposal and methodology
- Financial proposal or price schedule
- Company registration certificate
- Audited financial statements
- CVs of the proposed key experts
- References for similar contracts
- Signed declarations (eligibility, conflict of interest)