Improvement of Energy Efficiency and Energy Security of the Water Pumping Station, Partial Renovation of the Existing Water Supply Networks in Krasyliv 2026 Tender

In context

This is a contract notice published by a multilateral institution covering construction and works. Bids are invited through an open procedure. Delivery covers Ukraine (Europe). It is classified under Renewable Energy, Water and Energy Efficiency and 1 other against the sustainability taxonomy rather than matched on keywords.

Summary

Nefco is procuring two design-and-build lots in Krasyliv, Ukraine: solar PV installation at water supply facilities (Lot 1) and reconstruction of water networks on Shevchenka Street (Lot 2). Bidders with turnkey works experience in renewable energy or municipal water infrastructure, who can deliver within 10 to 11 months, fit best.

Summary by Raise Lens from the official notice · 27 Oct 2026Accurate?

Get the official link (free account)

Create a free account to open the official notice and application link: 1 official link a month, free. Pro opens every link.

About this tender

The project "Improvement of Energy Efficiency and Energy Security of the Water Pumping Station, Partial Renovation of the Existing Water Supply Networks in Krasyliv" aims to improve energy efficiency, energy security and reliability of the municipal water supply system in Krasyliv, Khmelnytskyi Oblast, Ukraine. It is financed by Norway through the Green Recovery Programme for Ukraine, with grant funds administered by Nefco. The invitation for tenders was published on 23.10.2026. The procurement is divided into two lots. Lot 1 covers installation of solar photovoltaic (PV) plants at water supply facilities, including supply and installation of equipment, related construction works and commissioning. Lot 2 covers reconstruction of water supply networks along Shevchenka Street in Krasyliv, including supply of equipment and materials, construction and installation works, and commissioning. Both lots are to be delivered on a Design & Build (turnkey) basis, including preparation of design and cost estimate documentation, required expert examination, designer's supervision and as-built documentation. Tenderers may bid for one or both lots. The procurement is conducted under Nefco's Procurement Policy and Procedures. Works are expected to start in March 2027, with completion periods of 10 months for Lot 1 and 11 months for Lot 2, counted from the respective contract effective dates.

Lots

  • Lot 1: Installation of solar photovoltaic (PV) plants at water supply facilities

    Supply and installation of PV equipment, related construction works and commissioning, delivered on a Design & Build (turnkey) basis including design and cost estimate documentation, expert examination, designer's supervision and as-built documentation. Completion period: 10 months from contract effective date.

  • Lot 2: Reconstruction of water supply networks along Shevchenka Street in Krasyliv

    Supply of equipment and materials, construction and installation works, and commissioning, delivered on a Design & Build (turnkey) basis including design and cost estimate documentation, expert examination, designer's supervision and as-built documentation. Completion period: 11 months from contract effective date.

Key requirements

  • ✓Turnkey design-and-build including design documentation, expert examination, designer supervision and as-built documentation
  • ✓Lot 1: supply, installation and commissioning of solar PV plants at water supply facilities
  • ✓Lot 2: supply of materials and reconstruction of water supply networks on Shevchenka Street, completion within 11 months

Procurement contact

The notice names a procurement contact for clarification questions.

About this sector

Renewable energy funding covers solar, wind, hydropower, geothermal and bioenergy, from early research to grid-scale deployment. Public money tends to back demonstration, grid connection and access to energy in emerging markets, while procurement notices buy installation, operation and maintenance. Calls often ask for proof of resource assessment, permitting progress and local partners.