New indoor GIS 132/20 kV substation with two 55 MVA transformers 2026 Tender

Original: Construcción de nueva subestación transformadora de 132/20 kV tipo GIS de interior con dos transformadores 132/20 kV, 55 MVA-ST. Autoridad Portuaria de Valencia 2

Consejo de Administración de la Autoridad Portuaria de Valencia

In context

This is a contract notice published by a government body covering construction and works. Delivery covers Spain (Europe). It is classified under Grid Modernization and Engineering and Infrastructure against the sustainability taxonomy rather than matched on keywords.

Summary

The Valencia Port Authority is procuring construction of a new indoor GIS 132/20 kV electrical substation with two 55 MVA transformers. It suits experienced electrical infrastructure contractors with high-voltage substation delivery track records, rather than small sustainability startups.

Summary by Raise Lens from the official notice · 27 Oct 2026Accurate?

Get the official link (free account)

Create a free account to open the official notice and application link: 1 official link a month, free. Pro opens every link.

About this tender

The contracting party, the Consejo de Administración de la Autoridad Portuaria de Valencia, is tendering the construction of a new indoor GIS-type 132/20 kV transformer substation equipped with two 132/20 kV transformers rated 55 MVA-ST. The tender is titled "Autoridad Portuaria de Valencia 2" and is classified as a works contract (Obras) under CPV 45232220 (construction works for substations). The tender is an open procedure with ordinary processing, published on the Spanish State Contracting Platform (PCSP) under file EC26-C02-02310. It is also flagged as funded by other European funds. The publication record shows the tender notice was published on 25/10/2026 and the related documents (initiation agreement, justification report, confidentiality note and confidentiality document) were posted on 26/10/2026. The place of execution is Valencia, Spain. The page does not state the contract duration or the detailed technical specifications. These would be in the tender documents (pliego), which were not available on the page text provided.

Key requirements

  • ✓Design and construction of a new indoor GIS 132/20 kV substation
  • ✓Supply and installation of two 132/20 kV transformers rated 55 MVA
  • ✓Requires high-voltage electrical infrastructure delivery experience and technical qualifications

CPV codes

Relevant sectors

Grid Mod tendersInfrastructure

About this sector

Grid modernisation covers transmission, distribution, smart meters, interconnectors and the software that balances a network with more variable supply. Funding comes as innovation calls for network operators and suppliers as well as large public tenders for equipment and works. Applicants are usually asked to show technical readiness and experience working with regulated network companies.