Skip to content
Raise Lens
TENDER · TED (EU)utilitymixed

Design and construction of 15kV cable-overhead power network, 3 parts 2026 Tender

Original: Construction work for electricity power lines – Wykonanie projektu budowlano-wykonawczego oraz robót budowlano-montażowych według tego projektu dla zadania pn. „Budowa kablowej oraz kablowo-napowietrznej sieci elektroenergetycznej SN 15kV” (3 Części)

ENERGA-OPERATOR S.A.

In context

This is a contract notice published by a utility covering a mix of works, supplies and services. Bids are invited through an open procedure. Delivery covers Poland and the European Union (Europe). It is classified under Grid Modernization, Electric Mobility and Engineering and Infrastructure against the sustainability taxonomy rather than matched on keywords.

Summary

This tender procures design documentation and construction/installation works for a 15kV medium-voltage cable and hybrid overhead-cable electricity distribution network in Kołobrzeg, Poland, including a charging station connection. Bidders must be construction/electrical engineering firms capable of delivering both detailed engineering design and full build-out of power infrastructure.

Summary by Raise Lens from the official notice · 17 Oct 2026Accurate?

Get the official link (free account)

Create a free account to open the official notice and application link: 1 official link a month, free. Pro opens every link.

About this tender

The buyer, ENERGA-OPERATOR S.A., is procuring design-and-build services for the project "Budowa kablowej oraz kablowo-napowietrznej sieci elektroenergetycznej SN 15kV" (construction of a underground and underground-overhead 15 kV medium-voltage power network). The tender is split into three parts. The excerpt provided describes only Part 1. Part 1 covers construction of an underground SN-15 kV cable network with a ZKSN-3 cable connection to supply a publicly accessible electric vehicle charging station in Kołobrzeg (gmina M. Kołobrzeg). The work is governed by a Functional-Utility Programme (PFU) and supplementary information, which form Annex 12 to the SWZ (tender documentation). The contract runs in two stages. Stage I is the detailed design (design-build documentation), including all legally required opinions, agreements and permits, plus acquisition of land rights and payment of associated fees and compensation. Stage II is the construction and assembly works, including all materials and related costs, carried out according to the design developed by the contractor, positively accepted and approved by the buyer in Stage I. The buyer states that completion of the contract will occur after 1 January 2028. Specific start dates and total duration are not given in the excerpt. Specific requirements: products, software and equipment must originate from EU member states or from qualifying third countries under the WTO Government Procurement Agreement or other EU trade agreements, with origin determined under Article 60(1) and (2) of Regulation (EU) No 952/2013. No ICT products, services or processes named in the national cybersecurity recommendations or high-risk vendor decisions may be used. The buyer will not accept equipment using fluorinated greenhouse gases with a GWP of 1 or more, citing Regulation (EU) 2024/573.

Lots

  • Lot 1: Część 1 – Budowa kablowej sieci elektroenergetycznej SN-15kV wraz ze złączem kablowym ZKSN-3 w celu zasilenia ogólnodostępnej stacji ładowania pojazdów w m. Kołobrzeg

    Design-build of an underground SN-15 kV cable network with ZKSN-3 cable connection to supply a public EV charging station in Kołobrzeg. Stage I: detailed design, permits, land rights. Stage II: construction works per approved design.

Key requirements

  • ✓Design and construction of 15kV medium-voltage cable and hybrid overhead-cable electricity network
  • ✓Connection to public EV charging station in Kołobrzeg
  • ✓Two-stage delivery: Stage I engineering design with permits and land acquisition; Stage II construction and installation
  • ✓All materials, software, products and equipment must originate from EU member states or WTO-signatory third countries
  • ✓Compliance with functional and operational programme (PFU)

Relevant sectors

About this sector

Grid modernisation covers transmission, distribution, smart meters, interconnectors and the software that balances a network with more variable supply. Funding comes as innovation calls for network operators and suppliers as well as large public tenders for equipment and works. Applicants are usually asked to show technical readiness and experience working with regulated network companies.