Design and construction works: grid connection of EV charging station, Domanin 2026 Tender

Original: Site preparation work – Wykonanie projektu budowlano-wykonawczego oraz robót budowlano-montażowych według tego projektu dla zadania pn. „Przyłączenie do sieci elektroenergetycznej ogólnodostępnej stacji ładowania pojazdów na dz. 27/1 obr. 8 Domanin”

ENERGA-OPERATOR S.A.

In context

This is a contract notice published by a utility covering construction and works. Bids are invited through an open procedure. Delivery covers Poland and the European Union (Europe). It is classified under Electric Mobility, Grid Modernization and Engineering and Infrastructure against the sustainability taxonomy rather than matched on keywords.

Summary

This tender procures design and construction of electrical grid connection infrastructure for a public EV charging station in Poland, including full engineering documentation and build-out. Bidders must be construction/electrical engineering firms capable of delivering integrated design-build projects with EU-origin materials and cybersecurity compliance.

Summary by Raise Lens from the official notice · 24 Oct 2026Accurate?

Get the official link (free account)

Create a free account to open the official notice and application link: 1 official link a month, free. Pro opens every link.

About this tender

The buyer, ENERGA-OPERATOR S.A., is procuring the design and construction of a connection to the electricity distribution network for a publicly accessible electric vehicle charging station on plot 27/1, obr. 8 Domanin. The contract covers the full project: design documentation, the associated construction works and all related materials and costs. The work is split into two stages. Stage I is preparation of the construction-execution design documentation, including all legally required opinions, approvals and decisions, and securing the legal title to the real estate needed for the project. This is based on the Functional-Utility Programme (PFU) and its supplementary information. Stage II is the construction and assembly works, carried out to the design approved by the buyer in Stage I. The buyer requires that the works use only software, materials, products and equipment originating from EU Member States or from third countries that are parties to the WTO Government Procurement Agreement or other EU international agreements granting reciprocal market access, with origin determined under Article 60(1) and (2) of Regulation (EU) No 952/2013. The works must not include ICT products, services or processes flagged as high-risk or negative under the Polish cybersecurity act and related Polish Public Procurement Law provisions. Detailed requirements are set out in the SWZ annexes (PFU, guidelines, standards and draft contract terms). Partial bids are not permitted, and the contract includes a warranty. The procedure is subject to EU-threshold rules. The expected duration is not stated on the page.

Key requirements

  • ✓Design and construction documentation for EV charging station electrical grid connection
  • ✓All materials and products must originate from EU member states or WTO-signatory third countries
  • ✓No ICT products/services flagged by Polish Cybersecurity Plenipotentiary may be used
  • ✓Two-stage delivery: Stage I design/approvals, Stage II construction execution
  • ✓Acquisition of necessary land titles and regulatory permits included

Relevant sectors

About this sector

Electric mobility funding supports electric vehicles, charging infrastructure, battery supply chains and fleet transition for buses, vans and trucks. Public authorities buy vehicles and charge points through tenders, while grants back pilots and manufacturing. Applicants usually need site plans, grid capacity checks and an operator for the finished assets.