District-heating plant construction work – Prequalification – Lot A Heating Centre
Original: District-heating plant construction work – Prækvalifikation - Entreprise A Varmecentral
PlanEnergi
- Value
- Not stated · check listing
- Closes
- 14 Dec 2026
- Where
- Denmark
- Contract
- Works · Utility
Free accounts: 1 official link a month · Pro: every link
In context
This is a contract notice published by a utility covering construction and works. Bids are invited through a restricted procedure. Delivery covers Denmark (Europe). It is classified under Heating and Cooling and Engineering and Infrastructure against the sustainability taxonomy rather than matched on keywords.
Summary
PlanEnergi is prequalifying bidders for a design-and-build contract to construct a new district-heating central plant (Entreprise A) at Skals, intended to secure stable heat supply and cut natural gas use. It suits experienced large EPC contractors with district-heating plant delivery track records rather than small startups.
Get the official link (free account)
Create a free account to open the official notice and application link: 1 official link a month, free. Pro opens every link.
About this tender
Skals Kraftvarmeværk, a district-heating operator, is procuring a new heat plant (varmecentral) to secure stable heat supply to its district-heating customers and to reduce natural gas consumption for heat production. The project proposal was prepared under the Danish Heat Supply Act (Varmeforsyningsloven) and approved by Viborg Kommune before this procurement. The new heat plant project is divided into four separate total-contract packages (totalentrepriser): A - Varmecentral (heat plant), B - Akkumuleringstank (accumulation tank), C - Transmissionsledning (transmission pipeline), and D - Elkabel (electrical cable). Each package is treated as an independent project with its own project economics, and each is built and commissioned without interdependence on the others. This notice concerns only Totalentreprise A - Varmecentral, which is a prequalification (prækvalifikation) stage. The page content does not state the contract duration, deliverables in detail, or the award timetable.
Bidder eligibility
Not stated in the provided page content. The title indicates a prequalification stage, but no bidder requirements, registrations, references, or financial thresholds are given.
How bids are scored
Not stated in the provided page content.
Lots
- Lot A: Totalentreprise A - Varmecentral
Construction of a new heat plant (varmecentral) as a total contract. This is the subject of the current notice.
- Lot B: Totalentreprise B - Akkumuleringstank
Accumulation tank as a separate total contract with its own project economics.
- Lot C: Totalentreprise C - Transmissionsledning
Transmission pipeline as a separate total contract with its own project economics.
- Lot D: Totalentreprise D - Elkabel
Electrical cable as a separate total contract with its own project economics.
Key requirements
- Turnkey design-and-build (totalentreprise) for a new district-heating central plant
- Prequalification stage; bidders must meet qualification criteria before tendering
- Lot A of four independent contracts (A heating centre, B accumulator tank, C transmission pipeline, D electrical cable)
Relevant sectors
How this compares
About this sector
About this sector
Heating and cooling funding supports heat pumps, district heating, thermal networks, efficient cooling and the removal of fossil boilers. It arrives through national support schemes, local authority programmes and procurement for heat networks. Applicants typically need heat demand assessments, a connection plan and an operator for the system.
Free accounts: 1 official link a month · Pro: every link
Get alerts for notices like this
Create a free account and we save a search for this sector and country, so new tenders like this one arrive in your weekly email.
Get alerts, free →Quick facts
Documents to prepare
We found no document list in this notice. Usually asked for in tenders and RFPs; typical only, not this buyer’s list. Check the official notice.
- Technical proposal and methodology
- Financial proposal or price schedule
- Company registration certificate
- Audited financial statements
- CVs of the proposed key experts
- References for similar contracts
- Signed declarations (eligibility, conflict of interest)